A contractor submitted a written bid of $82,000 for a school renovation. The next lowest bid was $124,000. The school board's purchasing officer noticed that the contractor's bid appeared to omit the HVAC line item shown on every other bid, but accepted the bid before asking any questions. The contractor discovered the clerical error the next morning and promptly sought to avoid the contract.
Which statement is most accurate?

Choose the Best Answer